Hatem Bridge HVAC Renovations

HVAC Renovation of Hatem Bridge Building

January 2014 – INTECaec submits the final design drawings, specifications, and cost estimates.

October 2014 – January 2015 – URS and INTECaec respond to shop drawing submittals and RFIs from the construction contractor. Document clarification letters are issued regarding Boiler Blend Pumps, Thermostats, VAV boxes, and Boiler Gas Piping.

January 2015 – Construction begins. INTECaec continues construction administration and attends monthly progress meetings on the HVAC renovations.