Brookeville Beer Farm hired INTECaec in May of 2015 to implement a renovation of their existing facility. INTECaec brought the facility up to code and provided an occupant load and code analysis. We designed a mechanical cooling and propane system, plumbing, power, and lighting while working to preserve historical elements of the architectural and interior design.

A loading dock, outdoor walk-in cooler, silos and landscape and water features were introduced into the design.  Building permit was obtained in early December, and construction was completed in late July of 2016.

  • Client: Brookeville Beer Farm
  • Project Year: 2015-2016
  • Total Square Footage: 4000
  • Team Members: Scott Kaufman, Paul Levine, Sandor Szokolai, Nelson Esteban, Israel Geyfman